Detector #33: Detector Recovery

Phase 2 swaps

Added by Matt N 3 months ago. Updated about 1 month ago.

Status:
Closed
Priority:
High
Assignee:
-
Category:
-
Start date:
09/12/2024
Due date:
% Done:

0%

Estimated time:

Description

We believe the case of most errors are due to corrosion of the cable and not the FEB. In this phase we plan on swapping the ribbon cables of the 70 FEBs on the detector to determine how many are recovering from this swap. This will also give us the only quantitative data we will have to date about ribbon cable swaps.

The swaps will happen in two steps, each 1/2 of the detector.

Actions #1

Updated by Matt N 3 months ago

  • Tracker changed from General to Detector
Actions #2

Updated by Matt N about 1 month ago

Completed. 88.3% success and we are moving to phase 3.

Actions #3

Updated by Matt N about 1 month ago

  • Status changed from New to Resolved
Actions #4

Updated by Matt N about 1 month ago

  • Status changed from Resolved to Closed